Replace roofing on hall, garage and rectory - hall and garage complete
Replace windows in the hall, bathrooms, behind the sacristy and including all classrooms (upper and lower) - hall and garage finished after weather good enough for outside trim
Cry room and Confessional repairs - awaiting scheduling
Handicap accessible hall restrooms - completion scheduled 9/15/2026
Phase 2:
Kitchen and hall updates and improvements - completion scheduled 9/15/2026
Electrical and plumbing upgrades - main hall area / restroom - completion scheduled 9/15/2026
Phase 3:
Repair outdoor drainage issues around hall / update plumbing - planning spring 2027
Repair and re-pavement of parking lot - planning spring 2027
Landscaping for hall and church - planning 2027
Phase 4:
basement CCD classrooms - planning 2027
Restore upstairs CCD parish classrooms - planning 2027
New HVAC - planning 2027
Project Funding Needs:
Thanks to your generosity, our current funds fully cover the cost of roofing, cry room, confessional, hall / rectory window replacement, handicap bathroom / accessible front door, kitchen remodel, and drainage update / repair. Additional funds are needed to continue the projects and planned renovations:
Phase 1 (Handicap accessible hall bathrooms): COMPLETED
Phase 2 (Kitchen and Hall updates): COMPLETED
Phase 3 (Drainage, Parking lot, Landscaping : awaiting estimates and definitive plans: APPROXIMATELY 50% FUNDED
Phase 4 (All aspects of the upstairs classrooms and basement): updated estimates and financials will be available as phase 3 nears completion
Every gift matters. Your generosity will help preserve and strengthen St. Paul Parish for current and future generations.
Yours in Christ,
Father Witt, and St Paul Parish council
Dustin Sudhoff (937-344-1590) Lindsey Reinhard (419-852-4446)
Matt Hart (419-852-2372) Michele Homan (419-852-1947)
Kevin Knapke (419-305-6869) Kim Knapke (419-852-3756)